Shelby Center for Science &
Technology, Huntsville - University of Ala-Huntsville
The project was 200,000 Square feet
building with 33 labs, 13 classrooms, 2 auditoriums, and 146 offices. Project included all plumbing, sheet metal
fabrication & installation, lab piping, and mechanical piping.
Boeing
Facility Maintenance, Huntsville, AL - Fite Bldg. Co.
The contract includes completed facility maintenance for the Boeing property
located at the Huntsville International airport and all Redstone Arsenal
facilities.
Madison
Street Parking Garage, HSV Hosp - Robbins & Morton
Madison Street Tower; 4 floors were constructed on top of a 4 story
Parking Deck to allow relocation of 84 beds into state-of-the-art Patient
Rooms. We installed all HVAC, plumbing and Medical Gas systems. The
infrastructure included 3 new Air-Cooled Chillers, pumps, heat exchangers, an
updated Medical Vacuum system, protective-isolation rooms, and heat recovery
systems.
Calhoun
Community College Math and Science Building - Consolidated
Construction
The project included complete HVAC ductwork, piping, domestic water, sanitary
waste and vent, new powerhouse, and acid waste systems for the three (3) floor,
84,000 square foot building.
HHS
Emergency Department Renovations - Robbins & Morton
The project was 40,000 square feet of new construction which included 33 exam
rooms, 6 trauma rooms, nurses stations and support
rooms. After this area became operational, renovations were
performed on the 25,000 square foot existing Emergency Department, providing
current-code compliant systems and enhanced comfort control. The project
consisted of installing all Plumbing, Mechanical, and Medical gas systems for
the expansion of the Emergency Department at Huntsville Hospital.
Replace
Primary Pumping Station Valves, Arnold Air Force Base - AEDC
Installation of (6) 24" cone valves, re-piping of existing pump
discharges, and installation of a new fire pump system with accompanying
electrical, painting, and abatement.
NASA
Energy Upgrade to Chilled Water Facility, Building 4473 - NASA
The project included the erection of a 1,000,000 gallon chilled water tank,
complete chilled water piping system with all associated equipment, electrical,
and new pump building.
Samford
University Boiler Plant #3 & Chiller Plant Expansion - Samford University
The project consisted of a complete new boiler house and chiller plant. Systems
included; all general trades, new boiler system, and chilled water system.
Crestwood
Medical Center, 30 Bed Addition - Hoar Construction
The project consisted of an additional 30 patient beds
constructed over the existing hospital. Systems included; medical gas, chilled
water, steam and condensate, domestic water, sanitary waste and vent. Major
equipment included a new 750 ton chiller and a 750 hp boiler system.
System
Software Engineering. Annex, Army Core of Engineers Ph 1
(SSEA)
- Fite
Bldg. Co.
The project consisted of the design and building of new 2 story,
80,000 square feet software engineering building. The project included complete
HVAC, piping, and plumbing systems with administrative, software test labs and highbay assembly area.
U/G
Sanitary/ Industrial Expansion Project - PCL
The 150,000 square-foot facility, when operational, will manufacture
film. This product is primarily used in the electronics industry.
Many areas of this plant are considered "clean room" spaces to assist
in the quality control of the finished product. The project consisted of all
piping work for the building utilities, including chilled water, hot water,
steam, condensate, compressed air, nitrogen, breathing air, domestic water, and
RO water. Also installed were all plumbing systems; roof drains, floor
drains, eyewash stations, and locker rooms. The HVAC system we installed
included 31 Central Station Air Handling Units, 2 Make-Up Air Units, several
variable air volume zones, HEPA filtration of multiple areas, and humidity
control. Five areas included Computer-Room Air Conditioning systems.
HH,
Replace AHU-3
- Huntsville
Hospital
Replacement of an existing, deteriorated AHU with a
new, modular 40,000 CFM AHU with variable volume within an existing mechanical
space in the center of the hospital.
HH,
Emergency Power Upgrade - Huntsville
Hospital
Support utilities (fuel oil, ventilation, exhaust stack, muffler installation)
to accompany the installation of a new Emergency Generator.
NASA
Bldg 4777 Install 2nd Hi Current Source - Johnson Controls, Inc
Install piping and equipment to provide heat removal from existing testing
machines.
Dunlop
Retrofit Design build (SES Expansion) - Simco Construction., Inc
The project consisted up new utility piping for the new addition.
HH-
Governor's Drive Bridge Replacement - Robbins & Morton
A replacement pedestrian bridge to support the
widening of Governors Drive. This bridge also conveys basic utilities from
Huntsville Hospital main to the Rehab facility; including steam, condensate,
oxygen, etc.
HH-Gallatin
Street Bridge
- Robbins
& Morton
A new pedestrian bridge connecting the Rehab facility with the new Governors Medical
Tower.
Industrial
Site Prep & Underground Piping - Austin AE COM
Provide underground piping systems; chilled water, chemical sewer, city water,
sanitary sewer, storm sewer systems.
Industrial
Chemical Sewer Piping
This project involves the installation of vertical
steam stripper columns, stainless steel above ground chemical waste storage
tanks, below ground HDPE storage tanks, multiple pump systems, heat exchangers,
HDPE, fiberglass and stainless steel piping systems.
HH
- Kitchen HVAC upgrade - Huntsville Hospital
Conditioned air upgrades for the existing kitchen at Huntsville Hospital main,
including a new AHU and distribution ducts.
Industrial
Chiller Installation
The project included assembling and installing a new 1200 ton chiller complete
with a 24" piping system to support the new plant expansion project.
Samford
University
- Divinity
Pipe Replacement
Industrial
Site Pipe Rack Piping - Austin AE COM
The project included a new 10,000 feet of 4" and
6" stainless pipe for the Resin building support. Systems include; Reverse
Osmosis water, Compressed Air, Nitrogen, Natural Gas, High Pressure Steam and
Condensate.
Industrial
Above Ground Plumbing & HVAC Package - Austin AE COM
The project included all above ground HVAC and plumbing work including; chilled
water piping, HVAC ductwork, exhaust ductwork, major equipment, controls,
insulation, boiler system, cooling tower piping, process water, domestic water,
tempered water, R.O. Water, chemical sewer, sanitary waste and vent, breathing
air, compressed air, storm piping, and all plumbing fixtures.
Goodyear
Gadsden Sheetmetal Contract
The project included all new HVAC system and process system for the plant
expansion.